Theory
is evaluated first at the end of the upwind start-up phase and written into the restart the scheme switch makes anyway. While further checks remain, the final phase writes its fields and the wall samples at every multiple of this interval; each new sample is evaluated while the solver keeps running. A relaxed that moves by more than 2 % on some wall stops the solver at once (writeNow), the new goes into the saved pressure field and the solver restarts from there; the first check within 2 % is recorded and ends the checks, and the normal write interval returns.
With several perforated tubes one schedule is used for all: the shortest interval among them.
Equations
| where | meaning | unit |
|---|---|---|
| Iteration of the -th check | - | |
| Last iteration of the upwind start-up phase (the first evaluation) | - | |
| Check interval (this setting) | iterations | |
| Maximum number of evaluations (Maximum K evaluations) | - | |
| Last iteration of the run | - | |
| Relaxed new loss coefficient | - |
Default and rule
- Default
- 100Measured
- Rule
100 iterations.
- Source
The 2 % threshold and the check scheme are based on a validation run of a two-baffle test muffler. Every restart disturbs SIMPLE for about 40 iterations ( +17 %, pressure residual about 0.4) whether changed or not, so the solver is restarted only for a real change. In a verification run on the same muffler the check at iteration 300 moved by 0.09 % and caused no restart. The interval of 100 iterations leaves the field time to respond to the previous ; it is the program's default and has not been varied in a study.
Valid range 10-5000
Values
10-5000 iterations.
Too short
A check soon after a restart sees a field that has not yet responded to the last ; keep the interval well above the 40 or so iterations a restart disturbs the solution.
Steady only
Transient runs make no checks.